The Process

I do one thing and do it well. Therefore, I have my process down to a science. A typical kitchen takes 5 – 7 days. And you can still use your kitchen normally throughout the week.

Day 1: Remove doors/drawer fronts which are taken to my workshop to get sprayed.
Day 2: The frames get prepped; degreased and sanded. Everything gets two coats of primer.
Day 3: Frames get painted first coat.
Day 4: Frames get painted second coat.
Day 5: Installation. We bring the doors back and everything gets put back together. Then we go over everything with a fine tooth comb.
Voila!! A brand new kitchen.
It’s a fairly painless process and you can function normally in your kitchen the entire week.